Home >> News Events >> Events >> Chullora Public School (Australia): Programme of Project Events

Chullora Public School (Australia): Programme of Project Events

Monday, October 16, 2023 - 00:00 to Thursday, December 7, 2023 - 00:00
Monday, February 5, 2024 - 00:00 to Thursday, April 11, 2024 - 00:00
Monday, April 29, 2024 - 00:00 to Thursday, July 4, 2024 - 00:00
Monday, July 22, 2024 - 00:00 to Thursday, September 26, 2024 - 00:00

Key Project Events:

The project over the next year and a half can be broken into three phases.

We hope to be able to report back after each of the following phases and provide an evaluation of the project outcomes.

To find out more about this project please click on the email link.

 

1. Testing and selection phase: 

  • 1st week of term 4 – 9th Oct – 12th Oct


2. Intervention phase:

  • Part 1- from 2nd week of term 4 – 16th Oct – 7th Dec 2023
  • Part 2 – 5th February 2024 – 11th April 2024
  • Part 3 – 29th April – 4th July 2024
  • Part 4 - Monday 22nd July  - Sep 26th 2024    

 

3. Post Testing and evaluation phase:

  • September 2024